    PM Sharif takes notice of Tarbela hydropower project incident File photo PM Sharif takes notice of Tarbela hydropower project incident

    Prime Minister Shehbaz Sharif has sought a detailed report on an accident at the Tarbela 5th Extension Hydropower Project, directing relevant authorities to establish the cause of the incident, assess the damage and determine responsibility.

    The development follows the collapse of a weak section of rock during excavation work, which allowed water to flow from an intake pit into a connecting tunnel and the powerhouse under construction.

    The Water and Power Development Authority (WAPDA) confirmed that all workers were safely evacuated and no casualties were reported.

    Shehbaz seeks details of incident and responsibility

    According to sources, the prime minister has directed officials to provide the background of the incident and submit all relevant facts, including details of the damage and the identification of those responsible.

    The report is also expected to cover the response measures taken by the authorities following the accident.

    WAPDA officials to inspect project site

    Senior WAPDA officials are scheduled to visit the site to assess the situation and examine the circumstances surrounding the rock collapse.

    According to the Ministry of Water Resources, officials will review all aspects of the incident before deciding whether a formal inquiry is necessary.

    The next course of action will be determined after the inspection and assessment, ministry officials said.

    WAPDA confirms workers safe after water enters tunnel

    A WAPDA spokesperson said the rock collapse occurred during excavation of the second bench of the connecting tunnel at the Tarbela 5th Extension Hydropower Project.

    The collapse allowed water to flow from the intake pit into the connecting tunnel and the powerhouse being constructed.

    Workers were immediately evacuated. WAPDA said no loss of life was reported.

    The spokesperson added that water had been completely drained from the intake pit, while efforts to remove water from the powerhouse were continuing.

    WAPDA rejects reports of main tunnel collapse

    WAPDA rejected reports claiming that Tarbela's Tunnel No. 5 had collapsed, describing them as incorrect.

    The authority clarified that there had been no damage to the project's main tunnel, the powerhouse under construction, the tailrace culvert or the switchyard.

    It also said no further water was entering the downstream work sites.

    Senior WAPDA officials, consultants and contractors are assessing the situation to determine the extent of the incident and identify challenges affecting the project.

    Tarbela Dam discharge exceeds 150,000 cusecs, alert issued

    Separately, water discharge from Tarbela Dam has exceeded 150,000 cusecs, prompting the local administration and dam authorities to issue alerts for communities along the Indus River.

    According to reports from Swabi, alerts have been issued in Topi, Jahangira, Batakara and Punita, with residents of settlements along the riverbanks advised to take precautions.